AQL Sample Size for Lot 4,000 — GI Inspection at AQL 1.0

ISO 2859-1:1999 Table II-A · Cross-verified against QIMA reference
Lot size 4,000 units
Inspection level GI
AQL level 1.0
Code letter G
Sample size 32 garments
Accept if defects ≤ 2
Reject if defects ≥ 3

What this means

For a production lot of 4,000 garments at GI inspection level with an AQL of 1.0 (critical-major boundary defects), ISO 2859-1 requires the buyer's QC inspector to pull 32 garments at random from across the lot. If they find 2 or fewer defects, the entire lot is accepted. 3 or more defects means the lot is rejected — the factory must then sort 100% of the lot, repair defective pieces, and re-present for inspection.

Inspection level note: Reduced inspection — used for low-risk products or trusted suppliers.

AQL tier: Strict major defect standard for premium brands.

Accept / reject decision table

Defects found in sampleDecision
0 defectsACCEPT
1 defectACCEPT
2 defectsACCEPT
3 defectsREJECT
4 defectsREJECT

Worked example — your shipment

Suppose your factory has produced 4,000 garments for a buyer who specified GI / AQL 1.0. The buyer's inspector arrives, opens 5-8 cartons at random, and pulls 32 garments across them.

If the inspector finds 2 defects in those 32 garments → lot ACCEPTED, container ships.

If the inspector finds 3 defects → lot REJECTED. You sort 100% of 4,000 pieces, repair, and re-present in 2-3 days.

How this combination compares

This is the GI / AQL 1.0 combination — the critical-major boundary sampling plan for GI inspection. If your buyer's PO sheet specified different parameters, here are the adjacent plans:

FAQ for Lot 4,000 · GI · AQL 1.0

What if I find exactly 2 defects?

2 defects = ACCEPT. The accept number is the maximum number of defects you can have in the sample without rejecting. Exactly at the limit is still acceptable.

What if I find 3 defects?

3 defects = REJECT. The reject number is the lowest defect count that fails the lot. There is no "borderline" — anything ≥ 3 triggers a reject.

Can I argue an inspection where I found 3 defects?

You cannot argue the math — the accept/reject thresholds come from the ISO 2859 statistical tables. What you can argue is the classification of each defect. If the inspector marked something as a Major defect that your buyer's spec sheet calls Minor, push back with the spec sheet in writing.

What's the underlying acceptance probability at AQL 1.0?

ISO 2859-1 plans are calibrated so that lots actually at the AQL value get accepted ~95% of the time. So a lot truly at 1.0% defect rate has a 95% chance of being accepted by this plan. Lots at 2× the AQL get rejected most of the time.

Use this in your own QC software

The same logic is published as a free MIT-licensed package:

$ npm install garment-aql-calculator
$ pip install garment-aql-calculator

// Node.js
const { calculateAQL } = require('garment-aql-calculator');
calculateAQL({ lotSize: 4000, inspectionLevel: 'GI', aql: 1.0 });
// → { codeLetter: 'G', sampleSize: 32, acceptNumber: 2, rejectNumber: 3 }