SAH in the Garment Industry: Standard Allowed Hours (Earned Hours) Formula and Calculator
Quick answer. SAH (standard allowed hours, or standard hours earned) is output measured in hours of standard work.
SAH = Σ(pieces produced × SAM) ÷ 60 · Efficiency % = SAH ÷ attended hours × 100
Illustrative example: a unit sews 760 T-shirts (SAM 8.50) and 450 shirts (SAM 22.00). SAH = (6,460 + 9,900) ÷ 60 = 272.67 hours. With 59 operators attending 8 hours (472 hours), efficiency = 272.67 ÷ 472 × 100 = 57.8%.
SAH calculator
Prefilled with the worked example. Leave unused rows empty. Runs in your browser.
Want this number from your own floor, every hour? Ask on WhatsApp →
Pieces are a poor way to compare sewing lines. A line that makes 760 T-shirts and a line that makes 450 shirts have not done work you can compare by counting, because a shirt takes far more sewing than a T-shirt. SAH fixes that by turning every garment into the hours of standard work it contains. Once output is in hours, you can add styles together, compare lines and factories, and divide by the hours you paid for to get efficiency.
What is SAH in the garment industry?
SAH (standard allowed hours, also called standard hours earned or earned hours) is output expressed as hours of standard work. Every piece is worth its SAM in minutes, so SAH = Σ(pieces × SAM) ÷ 60. Because it is measured in hours, it lets you add up and compare output of different styles.
SAH full form and other names
SAH is most often expanded in factories as standard allowed hours (common usage; Online Clothing Study calls the same measure standard hours earned or standard hours produced): the hour version of SAM, standard allowed minutes. Online Clothing Study uses several names for the same quantity. It calls it "Standard Hours Earned", notes it "is also called as Earned Hours because the operator has earned that many hours by his/her effort", and says it is "similar to Standard Minute Produced by workers. Instead of minutes, it is presented in hours" (What is Standard Hours Earned). Another article on the same site expands SAH as "Standard hours produced" (What is SAH hit rate). Whatever the label, the calculation is the same.
The SAH formula in the garment industry
SAH (earned hours) = Σ(pieces produced × SAM) ÷ 60
Efficiency % = SAH ÷ attended hours × 100
On-standard efficiency % = SAH ÷ worked hours × 100
Attended hours = operators × hours present. Worked hours = attended hours minus off-standard time such as waiting for work or machine breakdowns.
Online Clothing Study gives the earned standard hours formula as "Earned hours = (Number of pieces produced * Standard minute of the job)/60", where 60 converts earned minutes into hours. Its example: an operator sews 300 side seams at 0.80 SAM, so earns (300 × 0.80) ÷ 60 = 4 hours. When one operator does several operations, work out earned hours per operation and add them (Earned Hours Calculation Method).
SAM per operation gives operator SAH; SAM per garment, applied to finished garments, gives line or factory SAH. Setting that SAM is covered in SAM and SMV calculation in garments; SAH is only as accurate as the SAM behind it.
How do you calculate SAH in the garment industry?
Multiply the pieces produced by the SAM of each style or operation, add the results, and divide by 60. Illustrative example: 760 T-shirts at 8.50 SAM and 450 shirts at 22.00 SAM give (6,460 + 9,900) ÷ 60 = 272.67 standard hours earned. Divide by attended hours for efficiency.
Worked example: two lines, two styles
Illustrative example. Line A sews a crew-neck T-shirt (SAM 8.50, the breakdown from our SAM guide) with 19 operators. Line B sews a full-sleeve shirt (illustrative SAM 22.00, close to the 22.3 formal-shirt SAM in our SAM guide) with 40 operators. Both attend 8 hours.
| Line A: T-shirt | Line B: shirt | Both lines | |
|---|---|---|---|
| Pieces produced | 760 | 450 | 1,210 |
| SAM (min) | 8.50 | 22.00 | – |
| Standard minutes = pieces × SAM | 6,460 | 9,900 | 16,360 |
| SAH earned = minutes ÷ 60 | 107.67 | 165.00 | 272.67 |
| Attended hours = operators × 8 | 152 | 320 | 472 |
| Efficiency = SAH ÷ attended × 100 | 70.8% | 51.6% | 57.8% |
| SAH per operator | 5.67 | 4.13 | 4.62 |
Counting pieces, Line A looks far ahead: 760 against 450. In SAH, Line B produced more work, 165 hours against 107.67, because each shirt carries 22 minutes. But Line B also used more than twice the hours, so per hour paid Line A is the stronger line: 70.8% against 51.6%. Pieces said A was better for the wrong reason; SAH says it for the right one. This is the same efficiency you get from the minutes formula in sewing line efficiency calculation; SAH simply states it in hours, which is easier to add across lines and days.
Attended hours or worked hours?
Suppose Line B lost 20 operator-hours waiting for cut panels. Efficiency on attended hours stays 51.6%. On worked hours (320 − 20 = 300), on-standard efficiency is 165 ÷ 300 × 100 = 55.0%. The first tells you what the factory got for the hours it paid; the second isolates how the operators performed when they had work. Both are useful. Decide which one each report uses and keep it fixed, or week-to-week comparisons mean nothing.
What is the difference between standard hours and earned hours?
In garment use they are the same number seen from two sides: standard hours are what the output is worth at SAM, and the operator earns those hours by producing it. The comparison that matters is earned hours against attended or worked hours, because that ratio is efficiency.
SAM, SAH and "standard hours" in cost accounting
| Term | What it measures | Unit |
|---|---|---|
| SAM / SMV | Standard time for one operation or one garment, including allowances | Minutes per piece |
| SAH / earned hours | Pieces actually produced × SAM, converted to hours | Hours |
| Standard hours allowed (cost accounting) | Standard hours per unit × units actually produced | Hours |
| Standard hour (CIMA/ACCA usage) | Work achievable in an hour at the expected level of efficiency | Hours |
Accountants use closely related ideas. AccountingTools defines standard hours allowed as "the number of hours of production time that should have been used during an accounting period", calculated as standard hours per unit × actual units produced, and compared with actual hours in labour efficiency variance (AccountingTools). That is the same structure as SAH.
The difference to watch is the efficiency built into the standard. ACCA's study material defines a standard hour as "the amount of work achievable, at the expected level of efficiency, in an hour", and its efficiency ratio is expected hours of actual output ÷ actual hours worked × 100 (ACCA, The standard hour). A garment SAM is set at standard performance, not at the efficiency the factory expects, so 100% means something different in the two systems. When an IE report and a finance report disagree on efficiency, check which standard each one uses before arguing about the floor.
Weekly and monthly SAH as a capacity measure
ACCA notes that the standard hour is "especially useful as a common measure for combining heterogeneous (dissimilar) products". That is why SAH works for capacity: a unit's capacity in SAH does not depend on which style it runs.
Capacity (SAH) = operators × hours per day × working days × planned efficiency
Capacity (pieces) = capacity (SAH) × 60 ÷ style SAM
Illustrative example: the same 59 operators, 8 hours a day, 26 working days, planned at 60%: 59 × 8 × 26 × 0.60 = 7,363.2 SAH a month. That is 51,975 T-shirts at 8.50 SAM, or 20,081 shirts at 22.00 SAM, or any mix whose SAH adds up to 7,363.2. Planners can book orders against one hours figure instead of recalculating pieces for each style; converting an order into the operators it needs is covered in manpower calculation for a garment order, and the daily number for each line in line target calculation.
Online Clothing Study also tracks SAH hit rate: the days a line achieves its planned SAH divided by the days observed, × 100. In its example a line hits plan on 6 of 15 days, a hit rate of 40% (source). It shows how often the plan holds, which an average hides.
SAH for operators and pay
At operator level, SAH is the fairest single output number across operations of different lengths, which is why it sits among the sewing operator productivity metrics and the garment factory KPIs a production manager tracks. Online Clothing Study notes that once earned hours are known, an operator's earnings follow from the standard hourly rate (source). How pay is worked out from scanned output is covered in piece-rate payment calculation.
Common mistakes
- Counting rejected pieces. Pieces that go back for repair earn their SAM once; do not add them again when they come back. Rejected pieces that cannot be repaired earn no SAH: count only good pieces.
- Mixing operation SAM and garment SAM. For a line, use finished garments × garment SAM. Adding every operator's operation SAH as well counts the same work twice.
- Using an old SAM after a style change. A changed construction changes the SAM, and SAH with it.
- Switching between attended and worked hours. Pick one denominator for each report.
- Comparing SAH totals between lines of different sizes. Compare efficiency or SAH per operator, not raw SAH.
Where the inputs come from
SAH needs pieces by style or operation, the SAM for each, and attended hours. With QR bundle scanning in Scan ERP, each operator scans the bundle at their operation, so pieces per operation and per operator build up from the scans, and attendance comes from ZKTeco biometric punches. Live line efficiency then updates during the shift, and earned hours can be worked out from the same scans instead of being added up from tally sheets the next morning.
Sources
- Prasanta Sarkar, What is Standard Hours Earned (SAH) in Garment Manufacturing?, Online Clothing Study, June 2014.
- Prasanta Sarkar, Earned Hours Calculation Method, Online Clothing Study, January 2017.
- Prasanta Sarkar, What is SAH Hit Rate?, Online Clothing Study, January 2020.
- ACCA, The standard hour, MA1 technical article.
- Steven Bragg, Standard hours allowed definition, AccountingTools.
Santosh Rijal is the founder of Scan ERP, a garment manufacturing ERP system built for factory floor operations.
Earned Hours and Efficiency, Live
Scan ERP calculates this from QR bundle scans on your own floor: no manual tally, no end-of-day estimate. Ask the founder on WhatsApp and see it on a real line.
Ask on WhatsApp Request a Free Demo