What is inline inspection in the garment industry?
Inline inspection is quality checking done during sewing, at the operation or on the line, while the order is still being made. A checker examines pieces from individual operators, records defects by type, and gets each problem fixed at its source. It differs from end-line checks of finished garments and final AQL inspection of packed cartons.
How do you calculate DHU in an inline inspection report?
DHU (defects per hundred units) is total defects found ÷ pieces checked × 100. Defect % is defective pieces ÷ pieces checked × 100. One piece can carry several defects, so DHU can be higher than defect %. Example: 3 defects on 2 faulty pieces out of 40 checked gives DHU 7.5 and defect % 5.0.
Inline vs end-line vs final inspection
| Stage | When and where | What is checked | Main purpose |
|---|---|---|---|
| Inline | During sewing, at the operator's machine or on the line | Pieces from one operation and one operator at a time | Catch a fault at its source before more pieces are made with it |
| End-line | At the end of the sewing line | Complete garments as they come off the line | Stop defective garments going to finishing; feed rework |
| Final (AQL) | After packing, before shipment | A random sample of packed cartons | Decide whether the lot is accepted, using an AQL sampling plan |
Inline inspection does not replace the other two. Its value is timing: a skip-stitch found on the third piece of a bundle costs one repair, found at end-line it can cost a whole bundle of repairs.
Fields in a garment inline inspection report
Write the header once per sheet, then one row for each operator check.
Header (once per sheet)
- Date and shift
- Line (line or section number)
- Buyer, style and PO
- Checker (name or ID of the inline QC)
Each row (one operator check)
- Round time: when the check was done
- Operation: e.g. collar attach, side seam
- Operator ID: so defects are traced to the right person and machine
- Pieces checked
- Defects by type: one column per defect type (broken stitch, skip stitch, open seam, puckering, uneven stitch, other). Use your factory's own defect list.
- Total defects: sum of the defect-type columns
- Defective pieces: pieces with at least one defect
- DHU and defect %: see the formulas below
- Action taken: machine adjusted, operator retrained, pieces sent for rework
- Checker signature
DHU = Total defects ÷ Pieces checked × 100
Defect % = Defective pieces ÷ Pieces checked × 100
These are the same DHU formula and definition used in our DHU formula and benchmarks guide.
Inline Check DHU Calculator
Enter one operator check. DHU and defect % update as you type. Pre-filled with the example row below.
3 defects found on 2 defective pieces out of 40 checked.
Filled example: one inline check
An illustrative row, not data from a real factory. The DHU and defect % cells are calculated by this page from the counts.
Printable Blank Format
Print prints only this sheet, on A4 landscape. Or download the same columns as a CSV.
Inline Inspection Report
DHU = Total defects ÷ Pieces checked × 100 · Defect % = Defective pieces ÷ Pieces checked × 100 · Format: scanerp.pro/tools/inline-inspection-report-format.html
The traffic light system in inline inspection
Many factories run inline checks as a "traffic light" system. Each operator's latest check is shown as green, yellow or red on a card or board at the machine. Green means continue, while yellow and red mean the checker returns sooner and the fault is corrected before more pieces are sewn.
How many pieces to check per round, how often to check, and how many defects turn a result yellow or red are not universal numbers. Each factory sets its own, often to suit the buyer's requirements. Write your rules on the report so every checker applies the same ones.
About the CSV download
The download is a CSV file, not an .xlsx workbook. It opens in Excel, Google Sheets and LibreOffice, but it holds no formulas: the DHU and defect % formulas are written as notes at the top. It has the same columns as the printable format, plus date, line and buyer/style/PO as columns so each row stands alone, one illustrative example row to delete before use, and blank rows.
Related guides and tools
Stop Adding Up Tally Sheets. Let the Factory Do It.
In Scan ERP, checking is a scan point, so live DHU and defect-Pareto dashboards are fed by the scans, with zero manual entry.
Book a Free Demo